Perform desk review based on the Validation and Verification Report

  • Validation and/or Verification start with a Desk Review of the documentation. This step aims to review the compliance of a project with the Programme and the selected Methodology before site visits are conducted.
  • The VVB shall evaluate and document any material misstatements or nonconformity with ERS criteria. This includes performing cross-checks between the information provided in the PDD and information from sources other than those used. To facilitate the process:
    • VVBs should consider the Certification Report to see how ERS has evaluated every criteria.
    • VVBs should refer to the Validation and Verification Report to find all the criteria and their related data entry.
  • When performing Desk Review, VVBs should be paying particular attention to:
    • The Project coordinates, carbon rights, additionality demonstration.
    • Stakeholder consultations, including Stakeholder Mapping and FPIC.
    • The Restoration Plan including the species used, site preparation techniques and site assessments.
    • The Social Additionality Plan including social interventions and benefit sharing.
    • The Carbon Report, including calculations, the parameters used and the quality assurance and quality control procedures.
  • VVBs must consider the inputs received from the Public Comment Period and adjust the V&V Plan if needed, including the On-Site Visit schedule.
Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us