After completing the evidence-gathering activities, VVBs must complete the Validation/Verification Report and potentially issue the NC Report.
Developers must answer to nonconformities within 15 business days. VVBs must assess the answers to nonconformities within 10 business days.
The VVB shall resolve or “close out” CARs and CLs only if the Developer modify the PDD or provide additional explanations or evidence that satisfy the VVB’s concerns.
If after two rounds, another round is required, the VVB must renegociate the terms of the Project Mandate.
The VVB shall update the V&V report according to any corrections, changes, CARs, CLs, FARs requested during the process.