Complete and upload the Non-Conformity Report

  • After completing the evidence-gathering activities, VVBs must complete the Validation/Verification Report and potentially issue the NC Report.
  • Developers must answer to nonconformities within 15 business days. VVBs must assess the answers to nonconformities within 10 business days.
  • The VVB shall resolve or “close out” CARs and CLs only if the Developer modify the PDD or provide additional explanations or evidence that satisfy the VVB’s concerns.
  • If after two rounds, another round is required, the VVB must renegociate the terms of the Project Mandate.
  • The VVB shall update the V&V report according to any corrections, changes, CARs, CLs, FARs requested during the process.
Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us